Answer:
B. about $2,589
Step-by-step explanation:
Given data
P=$1,800
R= 3.7%
T=10years
The expression for the compound interest is given as
A= P(1+r)^t
substitute
A= 1800(1+0.037)^10
A= 1800(1.037)^10
A=1800*1.43809495884
A=$2588.570
Hence the answer is B. about $2,589
Answer:
You have a number multiplied by the variable x, so three times some value x. then you have (-y) taking the value of 3x and subtracting the value of (y) from it. The expression depends on the values of x and y you plug into it.
Step-by-step explanation:
for example, 3(4) - (6) = 12-6 = 6
Answer:
(a) The inequality for the number of items, x, produced by the labor, is given as follows;
250 ≤ x ≤ 600
(b) The inequality for the cost, C is $1,000 ≤ C ≤ $3,000
Step-by-step explanation:
The total time available for production = 1000 hours per week
The time it takes to produce an item on line A = 1 hour
The time it takes to produce an item on line B = 4 hour
Therefore, with both lines working simultaneously, the time it takes to produce 5 items = 4 hours
The number of items produced per the weekly labor = 1000/4 × 5 = 1,250 items
The minimum number of items that can be produced is when only line B is working which produces 1 item per 4 hours, with the weekly number of items = 1000/4 × 1 = 250 items
Therefore, the number of items, x, produced per week with the available labor is given as follows;
250 ≤ x ≤ 1250
Which is revised to 250 ≤ x ≤ 600 as shown in the following answer
(b) The cost of producing a single item on line A = $5
The cost of producing a single item on line B = $4
The total available amount for operating cost = $3,000
Therefore, given that we can have either one item each from lines A and B with a total possible item
When the minimum number of possible items is produced by line B, we have;
Cost = 250 × 4 = $1,000
When the maximum number of items possible, 1,250, is produced, whereby we have 250 items produced from line B and 1,000 items produced from line A, the total cost becomes;
Total cost = 250 × 4 + 1000 × 5 = 6,000
Whereby available weekly outlay = $3000, the maximum that can be produced from line A alone is therefore;
$3,000/$5 = 600 items = The maximum number of items that can be produced
The inequality for the cost, C, becomes;
$1,000 ≤ C ≤ $3,000
The time to produce the maximum 600 items on line A alone is given as follows;
1 hour/item × 600 items = 600 hours
The inequality for the number of items, x, produced by the labor, is therefore, given as follows;
250 ≤ x ≤ 600
(a) The inequality for the number of items, x, produced by the labor, is given as follows;
250 ≤ x ≤ 600
(b) The inequality for the cost, C is $1,000 ≤ C ≤ $3,000
Inequality is a statement shows greater the, greater then equal to, less then,less then equal to between two algebraic expressions.
The total time available for production = 1000 hours per week
The time it takes to produce an item on line A = 1 hour
The time it takes to produce an item on line B = 4 hour
Therefore, with both lines working simultaneously, the time it takes to produce 5 items = 4 hours
The number of items produced per the weekly labor = 1000/4 × 5 = 1,250 items
The minimum number of items that can be produced is when only line B is working which produces 1 item per 4 hours, with the weekly number of items = 1000/4 × 1 = 250 items
Therefore, the number of items, x, produced per week with the available labor is given as follows;
250 ≤ x ≤ 1250
Which is revised to 250 ≤ x ≤ 600 as shown in the following answer
(b) The cost of producing a single item on line A = $5
The cost of producing a single item on line B = $4
The total available amount for operating cost = $3,000
Therefore, given that we can have either one item each from lines A and B with a total possible item
When the minimum number of possible items is produced by line B, we have;
Cost = 250 × 4 = $1,000
When the maximum number of items possible, 1,250, is produced, whereby we have 250 items produced from line B and 1,000 items produced from line A, the total cost becomes;
Total cost = 250 × 4 + 1000 × 5 = 6,000
Whereby available weekly outlay = $3000, the maximum that can be produced from line A alone is therefore;
$3,000/$5 = 600 items = The maximum number of items that can be produced
The inequality for the cost, C, becomes;
$1,000 ≤ C ≤ $3,000
The time to produce the maximum 600 items on line A alone is given as follows;
1 hour/item × 600 items = 600 hours
The inequality for the number of items, x, produced by the labor, is therefore, given as follows;
250 ≤ x ≤ 600
Hence the inequality for the number of items, x, produced by the labor, is 250 ≤ x ≤ 600 and the inequality for the cost, C is $1,000 ≤ C ≤ $3,000
To know more about Inequality follow