Answer:
decrease
1. fixed cost is 100
variable cost is 10
price = 20
100 / ( 20 - 10) = 10
2. fixed cost is 100
variable cost is 10
price = 30
100 / (30 - 10) = 5
Explanation:
Answer:
Explanation:
Considering the graph in the attached image, at point A, the economy was in the equilibrium, after an increase in the inflation target, the Ad curve will shift to the AD2. At this point the price is P* and the output is Y'. The new equilibrium is At B.
In the scenario given in the question, the worker will demand a higher wage as the real wages decline.
An increase in the wage will act as a negative supply shock and the demand curve will shift to the left i.e. SRAS2. The output will decrease and the price will increase. The new output will be at Y and equilibrium at C.
Therefore, increasing the inflation target will only increase the demand in the short run, and only increase the price in the market in the long run.
Answer:
Fixed Cost:
Total remains unchanged at total level.
And are variable at unit level, increase at lower level and decrease as higher level.
Variable Cost:
At unit cost, are the same, are the cost of producing one unit.
At total variable cost, it will increase along with sales and decrease when the sales are lower.
Explanation:
The unit fixed cost will be variable at unit level. As this amount will be distribute over more or less units.
So an increase of sales, decrease the unit fixed cost
and decrease of sales, increase the unit fixed cost
At total level, the fixed cost are the same for hte relevant range.
Answer:
Net Income = $ 1.05 million; you can calculate the amount using the profit margin which will be the 7% from the sales.
ROE = 19.8%, the formula is Net Income/Owners Equity. To obtain the amount for Owners Equity you can use the information provided using the Assets and the Total Debt, the difference will be the amount for Owners Equity $ 5.3million.
ROA = 11.7% , the formula is Net Income/Assets.
Answer and Explanation:
The journal entries are shown below:
1. On July 1 2019
Machinery Dr $67,000
Fixture & Fittings Dr $68,000
Vehicles Dr $35,000
Current assets Dr $12,000
Goodwill Dr $28,000
To Current liabilities $18,000
To Share Capital (80,000 × $1 ) $80,000
To Paid in capital in excess of par 112,000 {80,000 × ($2.40 - $1)}
(Being the acquisition is recorded)
For recording this we debited all assets as it increased the values of assets and credited the liabilities and stockholder equity as it also increased
2. On July 1 2019
Paid in capital in excess of par $1,600
To Cash $1,600
(Being the share issuance cost is recorded)
For recording this we debited the paid in capital as it reduced the stockholder equity and credited the cash as it reduced the assets
Working notes:
For goodwill amount
= Purchase consideration - net identifiable assets
= $192,000 - $164,000
= $28,000
The net identifiable asset come from
= $67,000 + $68,000 + $35,000 + $12,000 - $18,000
= $164,000
Answer:
Job 33 $ 27250
Job 34 $ 31500
Job 35 $ 12325
Cost of Goods Sold Job 33 $ 27250
Finished Goods Inventory Job 34 $ 31500
Work in Process Inventory Job 35 $ 12325
Explanation:
Work in Process Balance on 3/1
Job 33 $ 7,500
Job 34 6,000
Total $ 13,500
Job 33
Direct Materials $3500
Direct Labor 6500
Overheads (150%) 9750
Add Opening WIP 7500
Total Cost $ 27250
We add the Direct Material Direct Labor and Mfg overheads with the opening balance of WIP to get the total cost of given jobs.
Job 34
Direct Materials $6000
Direct Labor 7800
Overheads (150%) 11700
Add Opening WIP 6000
Total Cost $ 31500
Job 35
Direct Materials $4200
Direct Labor 3250
Overheads (150%) 4875
Add Opening WIP ------
Total Cost $ 12325
Cost of Goods Sold Job 33 (given) $ 27250
Finished Goods Inventory Job 34 (given) $ 31500
Work in Process Inventory Job 35(given)$ 12325
It is given in the question that Job 34 is transferred to Finished Goods , Job 35 is still in process and Job 33 is cost of goods sold.
By accounting for beginning balances, cost of materials, labor, and overheads, the costs of Jobs 33, 34, and 35 at end of the month are $27,250, $31,500 and $12,325 respectively. The Work in Process Inventory is $12,325, Finished Goods Inventory is $31,500 and Cost of Goods Sold is $27,250.
To calculate the cost of each job at Oak Creek Furniture Factory (OCFF), we first need to consider all cost factors. These include the beginning balances, additional materials requisitioned, labor hours, and overheads. Job overheads for OCFF are applied as 150 percent of direct labor cost.
Job 33: The initial cost was $7,500. During March, materials costing $3,500 and labor cost of $6,500 were added, making a total of $10,000. Applying the overhead calculation, we find that overheads amount to $6,500 * 1.5 = $9,750. The total cost for job 33 is therefore $7,500 (beginning balance) + $10,000 (material and labor costs) + $9,750 (overhead) = $27,250.
Job 34: Initial cost was $6,000. Material and labor costs for March amount to $6,000 and $7,800 respectively, summing up to $13,800. The overhead equals $7,800 * 1.5 = $11,700. The total cost for job 34 is accordingly $6,000 (beginning balance) + $13,800 (material and labor costs) + $11,700 (overhead) = $31,500.
In regard of Job 35, which is still in progress, only the cost of materials $4,200 and labor $3,250 have been added, totalling $7,450. Calculating overheads, we get $3,250 * 1.5 = $4,875. Therefore, the cost so far for job 35 is $7,450 (material and labor costs) + $4,875 (overhead) = $12,325.
For the balance of the Work in Process Inventory, we just include the cost of Job 35, which isn't finished yet: $12,325.
The Finished Goods Inventory includes the cost of Job 34 which is completed but not sold: $31,500.
Cost of Goods Sold consists of completed and sold jobs, in this case only Job 33: $27,250.
#SPJ3