Answer: template method
Explanation:
The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as template method.
It should be noted that estimating time and cost are vital because it helps schedule work, develop needs of cash flow and show progress of a project.
The bottom-up approach for estimating costs and times using information from similar past projects is called analogous estimating. This method, used in project management, relies on previous experience and expert judgment.
The method you're referring to is the analogous estimating. In project management, analogous estimating is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. This bottom-up approach is most reliable when the previous activities are similar in fact and not just in appearance to the current activity. This technique relies heavily on experience, expert judgment, and the project history to predict costs and timelines for a new project.
#SPJ3
Answer:
From Year 1 to Year 2 : There is annual deflation 11.11%
As price falls, value of money rises
Explanation:
Given : Commodity Basket Cost = $9 in Year 1 ; Commodity Basket Cost = $8 in Year 2
From Year 1 to Year 2 : There has been fall in price level. Proportionate (%) Fall in price level = Change in Price / Old Price x 100
So, Fall in price level = [ ( 9 - 8 ) / 9] x 100 = 1/9 x 100 = 11.11%
Hence, from year 1 to year 2 : there has been 11% fall in price i.e Deflation
Considering Income = $72 :
So, it illustrates that : As price falls, the purchasing power of money (value of money) rises.
Answer:
$242.31
Explanation:
Purchasing cost of 100 shares a year ago = 315,000 yen
Today, 1 share = 3,465 yen
100 shares = 100×3,465 yen = 346,500 yen
Proceeds = 346,500 yen - 315,000 yen = 31,500 yen
Today, $1 = 130 yen
31,500 yen = $31,500/130 = $242.31
Answer:
a) 5.45%
b) 6.98%
Explanation:
We are given the following information in the question:
Mean, μ = 0.8%
Standard Deviation, σ = 2%
We are given that the distribution of profit is a bell shaped distribution that is a normal distribution.
Formula:
a) We have to find the value of x such that the probability is 0.99
P(X < x)
Calculation the value from standard normal z table, we have,
Thus, 5.45% of assets does the company need to be 99% sure that it will have a positive equity at the end of the year.
b) We have to find the value of x such that the probability is 0.999
P(X < x)
Calculation the value from standard normal z table, we have,
Thus, 6.98% of assets does the company need to be 99% sure that it will have a positive equity at the end of the year.
Answer:
journal entries to make are as shown below: DAKOTA MINING CO
question 1
Date Transaction Debit credit amount
July 23 land purchase Land account $ 4,715,000
july 23 land purchase Bank $ 4,715,000
question 2
July 25 Machine cost machine account $410,000
July 25 Machine cost bank $410,000
December 31 depletion 5 months profit $441,600
December 31 depletion mine reserve $0.92/ton
December 31 Depreciation profit $441,600
December 31, depreciation land $441,600
Explanation:
Purchase of fixed asset: the asset account usually have debit balances, so you debit the asset account and credit Dakota bank account where the money was paid out. The land account and machine accout will have the purchase cost/installation cost as debit balances(entries) respectively while Dakota Mining co bank account will be credited with the respective amounts $ 4,715,000 -land purchase and $410,000- machine cost/installation.
The depletion quantity in 5 months was given. using ratio we extrapolate the depletion quantity was a full year as 1,152,000 QTY (12/5 X 480,000)
= 1,152,000 QTY the useful life of the mine is then calculated by dividing the reserve amount by the annual production of 1,152,000 = 4.448784 yrs
depreciation annually = divide cost of land by useful life = $1.059,840
5 months depreciation = 5/12 x annual depreciation = $441,600
depletion per ton is gotten as follows: divide $441,600 by 480,000 tons mined for 5 months = 0.92/ton depletion rate
Answer:
Option (b) is correct.
Explanation:
Given that,
Net sales = $4,885,340
Cost of goods sold = (2,942,353 )
Selling expenses = (884,685 )
Operating income = $1,058,302
Interest expense = $(55,240 )
Earnings before income taxes = $1,003,062
Income tax expense = $(401,225 )
Net income = $ 601,837
EBIT = Net income + Income tax expense + Interest expense
= $1,003,062 + $401,225 + $55,240
= $1,058,302
Times interest earned ratio in 2017:
= EBIT ÷ Interest expense
= $1,058,302 ÷ $55,240
= 19.1582 or 19.16
Answer:
$66,000
Explanation:
The computation of the total implicit cost per year is shown below:
= Given up salary + investment amount × interest rate on investment in the economy
= $60,000 + $100,000 × 6%
= $60,000 + $6,000
= $66,000
We simply added the given up salary and investment amount after considering the interest rate on investment so that the accurate amount could come