Answer:
(i) and (iv)
Explanation:
The appreciable cost is the cost in which the assets can be depreciation over the useful life
And, the appreciable cost is come after deducting the salvage value from the acquisition cost
The formula to compute the depreciation expense using the straight-line method is shown below:
= (Original cost - salvage value) ÷ (useful life)
So it can be calculated after considering the first and four options
Answer:
a) the correct answer is "B"
b) the correct answer is "C"
Explanation:
a) the correct answer is "B"
relies on nominal GDP which might have increased because of price increases and not output increases. As nominal GDP accounts for the price and it is calculated at the current price level. The answer is "B".
b) the correct answer is "C"
We can ask for growth rate of real GDP which excludes price change.
b. encounter—where the newcomer learns what the organization is really like; and
c. change and acquisition—where members master important tasks and roles.
d. This process can be achieved through a variety of processes and tactics.
e. This exercise will challenge your understanding of some of the characteristics of these tactics and processes.
Answer: The correct answers are "a. anticipatory socialization—those activities that take place prior to the first day on the job;", "b. encounter—where the newcomer learns what the organization is really like;" and "c. change and acquisition—where members master important tasks and roles.".
Explanation: The 3 steps or phases of the organizational socialization process are:
1) Anticipatory socialization: those activities that take place prior to the first day on the job;
2) Encounter: where the newcomer learns what the organization is really like;
3) Change and acquisition: where members master important tasks and roles.
C Variable Cost Fixed
D Variable Cost VariableA) Choice C B) Choice D C) Choice A D) Choice B
Answer:
The correct answer is letter "B": Choice D.
Explanation:
Fixed costs are business expenses that do not change when production levels increase or decrease. These are one of two types of business expenses and the other is variable costs. Variable costs change with increases or decreases in production volume. Then:
1)The wages paid to the taco makers and other employees - Variable Costs
2)Materials (e.g., cheeses, salsa, tomatoes, lettuce, taco shells, etc.) used to make the tacos - Variable Costs
Answer:
11.15%
Explanation:
Given that
Risk free rate of return= 5%
Beta = 1.69
Expected rate of return = 15.4%
As per capital asset pricing model
Expected rate of return = Risk free rate of return + Beta × (Market rate of return - risk free rate of return)
15.4% = 5% + 1.69 × (Market rate of return - 5%)
After solving this
Market rate of return = 11.15%
Period Demand F1 F2
1 68 63 66
2 75 70 67
3 70 75 70
4 74 69 72
5 69 70 73
6 72 68 75
7 80 70 77
8 78 74 84
Required:
Compute MAD for each set of forecasts. Given your results, which forecast appears to be more accurate
Answer:
Kindly check explanation
Explanation:
Given the data:
Period Demand F1 F2
1 68 63 66
2 75 70 67
3 70 75 70
4 74 69 72
5 69 70 73
6 72 68 75
7 80 70 77
8 78 74 84
Mean absolute deviation (MAD) for F1:
P___Demand(D) __F1__F2___|D - F1|___|D-F2|
1____ 68 _______63 __66____5______ 2
2____75_______ 70__ 67____ 5______ 8
3____70_______ 75__ 70____ 5______ 0
4____74_______ 69__ 72____ 5______ 2
5____69_______ 70__ 73____ 1______ 4
6____72_______ 68__ 75____ 4______3
7____80_______ 70__ 77____ 10 _____3
8____78_______ 74__ 84____ 4______6
Mean absolute deviation (MAD) For F1 :
Σ(|D - F1|)/n :
(5 + 5 + 5 + 5 + 1 + 4 + 10 + 4) / 8
= 39 / 8
= 4.875
Mean absolute deviation (MAD) For F2 :
Σ(|D - F2|)/n :
(2 + 8 + 0 + 2 + 4 + 3 + 3 + 6) / 8
= 28 / 8
= 3.50
F2 seems to be more accurate has it has a Lower MAD value
To determine which forecast is more accurate between F1 and F2, the Mean Absolute Deviation (MAD) for each was calculated. It was found that Forecast F2, with a lower MAD of 3.75 compared to F1's 5.25, is the more accurate forecast.
The subject of this examination pertains to a field in mathematics known as forecasting. The Mean Absolute Deviation (MAD) is a commonly used method to measure the accuracy of forecast predictions. It is computed by taking the absolute value of the actual demand minus the forecasted demand, and then finding the average of these absolute differences over a specific period.
For F1: |68-63| + |75-70| + |70-75| + |74-69| + |69-70| + |72-68| + |80-70| + |78-74|. When you calculate these absolute differences and then divide the sum by 8 (number of periods), you get a MAD of 5.25.
For F2: |68-66| + |75-67| + |70-70| + |74-72| + |69-73| + |72-75| + |80-77| + |78-84|. Similarly, calculate these absolute differences and divide the sum by 8, you get a MAD of 3.75.
Given the results, the F2 forecast appears to be more accurate as it has a smaller MAD.
#SPJ3
Answer: internally homogenous
Explanation:
Since the potential customers belong to the same segment, display comparable characteristics, and choose the same product qualities that are consistent with their segment, then the condition for the ideal market segment approach which should be used is the internally homogeneous.
On the other hand, if the potential customers are in different segments, have different characteristics, and choose different product qualities, then the externally homogeneous will be ideal.
internally homogenous