16 men are employed to do a work in 20 days. at the end of 12 days the work is only half done. how many additional number of men should be employed to complete the work in the stipulated time?

Answers

Answer 1
Answer: 16 men in 12 days can do 0.5work
1 man 1 day can do 0.5/(16x12) of a work

8days to do 0.5 of a work
1 man 8 days can do 8x0.5/(16x12) = 0.5x(1/24) of a work
... if you notice we need 24 men

... more detail
in8days, 0.5x(1/24) of a work need 1 man
in8days, 0.5 of a work need 0.5/(0.5x(1/24)) = 24 men

point is to find 'amount of work done per man per unit of time' then work out from that.

Related Questions

Please help me... I will crown you Brainlyest
Sammy has $0.37 in his pocket he only has four coins.What coins does he have in his pockets??
Find three consecutive numbers whose sum is 138 by writing and solving an equation
Ben wants to put a dog fence around an areain his yard. If the length is 5 feet longer than itswidth and Ben uses 70 feet of fencing, what arethe dimensions of the enclosed area? PLEASE HURRY
Does the table represent an exponential function?|X: 1|2|3|4| |Y: 4|8|12|16| -Yes -no

Two ships leave whittier, Ak at 7 AM. The first ship sails towards Valdez on a 54° course at a constant rate of 36 mi/h. The second ship sails towards Knight island on a 144° course at a constant speed of 42 mi/h. Find the distance between the ships at 11 AM.

Answers