Answer:
Step-by-step explanation:
It would take a work crew of 4 people approximately 5 days and 18 hours to complete the same job if each person in both crews works at the same rate as each other.
To solve this problem, we can start by calculating the total work done by the original work crew of 3 people in terms of "work-weeks." We know that they require 3 weeks and 2 days to complete the job.
1 week = 7 days
So, 3 weeks and 2 days can be converted to days as follows:
3 weeks + 2 days = 3 weeks + (2/7) weeks
≈ 3 weeks + 0.2857 weeks
≈ 3.2857 weeks
Now, we know that the original work crew of 3 people completes the job in 3.2857 work-weeks.
Next, we can calculate the amount of work done by each person of the original crew per work-week:
Work done by 1 person in 1 week = 1/3 of the total work (as there are 3 people)
Work done by 1 person in 1 work-week ≈ 1/3.2857
Now, we want to find out how much work a single person of the new work crew of 4 people can do in 1 work-week. Since each person in both crews works at the same rate, the work done per person per week will be the same.
Work done by 1 person in 1 work-week ≈ 1/3.2857 ≈ 0.3043
Now, we know that a single person from the new crew can complete approximately 0.3043 of the total job in one work-week.
Finally, we want to find out how long it will take for the new work crew of 4 people to complete the entire job. Let's denote the time in weeks as "x."
Total work done by the new crew of 4 people = 4 people * x weeks * 0.3043 work done per person in 1 week
Total work done by the new crew of 4 people = 1 job (as they will complete the entire job)
So, we have the equation:
4x * 0.3043 = 1
Now, solve for "x":
x ≈ 1 / (4 * 0.3043)
x ≈ 0.8225
Therefore, it would take a work crew of 4 people approximately 0.8225 weeks to do the same job. To convert this into days:
0.8225 weeks * 7 days/week ≈ 5.7575 days
So, it would take a work crew of 4 people approximately 5 days and 18 hours to complete the same job if each person in both crews works at the same rate as each other.
For more details of work crew:
#SPJ2
Answer:
Step-by-step explanation:
Using perimeter =2(l+b)
74=2(L+B)
From the question
Width(b)=x & length(l)=3x+5
So we have that
74 =2(3x+5+x)
Adding like terms we then have that
74 =2(4x+5)
Opening the bracket gives
74=8x +10
Collecting like terms
8x=74-10
8x= 64
Therefore
X=64/8
X=8feets
The width is 8feets
Answer:
8 feet.
Step-by-step explanation:
plug into missing values
Answer:
(P-2l)/2 =w
Step-by-step explanation:
P = 2l + 2w
Subtract 2l from each side
P -2l = 2l-2l + 2w
P-2l = 2w
Divide by 2
(P-2l) /2 = 2w/2
(P-2l)/2 =w
Answer:
Step-by-step explanation:
B. y = -3y + 2
C. y = 3y - 2
D. y = -3y - 2
The equation that represents the line shown in the graph is:
B. y = -3x + 2
Solving linear equation mean calculating the unknown variable from the equation.
Let the linear equation : y = mx + c
If we draw the above equation on Cartesian Coordinates , it will be a straight line with :
m → gradient of the line
( 0 , c ) → y - intercept
Gradient of the line could also be calculated from two arbitrary points on line ( x₁ , y₁ ) and ( x₂ , y₂ ) with the formula :
If point ( x₁ , y₁ ) is on the line with gradient m , the equation of the line will be :
Let us tackle the problem!
From the graph , the line goes through the point ( -1 , 5 ) and ( 0 , 2 ).
Let:
( x₁ , y₁ ) = ( 0 , 2 )
( x₂ . y₂ ) = ( -1 , 5 )
We can calculate the gradient of the graph by using this following formula:
Next , we can find the equation of the graph by using this following formula:
Grade: High School
Subject: Mathematics
Chapter: Linear Equations
Keywords: Linear , Equations , 1 , Variable , Line , Gradient , Point
Answer:
B) sqrt 3/3 (I don't know how to add the square root or fraction symbols)
Step-by-step explanation:
Did the quiz