A work crew of 3 people requires 3 weeks and 2 days to do a certain job. How long would it take a work crew of 4 people to do the same job if each person of both crews works at the same rate as each of the others. [Note: each week contains six work days]Thanks for the help!

Answers

Answer 1
Answer:

It would take a work crew of 4 people approximately 5 days and 18 hours to complete the same job if each person in both crews works at the same rate as each other.

To solve this problem, we can start by calculating the total work done by the original work crew of 3 people in terms of "work-weeks." We know that they require 3 weeks and 2 days to complete the job.

1 week = 7 days

So, 3 weeks and 2 days can be converted to days as follows:

3 weeks + 2 days = 3 weeks + (2/7) weeks

≈ 3 weeks + 0.2857 weeks

≈ 3.2857 weeks

Now, we know that the original work crew of 3 people completes the job in 3.2857 work-weeks.

Next, we can calculate the amount of work done by each person of the original crew per work-week:

Work done by 1 person in 1 week = 1/3 of the total work (as there are 3 people)

Work done by 1 person in 1 work-week ≈ 1/3.2857

Now, we want to find out how much work a single person of the new work crew of 4 people can do in 1 work-week. Since each person in both crews works at the same rate, the work done per person per week will be the same.

Work done by 1 person in 1 work-week ≈ 1/3.2857 ≈ 0.3043

Now, we know that a single person from the new crew can complete approximately 0.3043 of the total job in one work-week.

Finally, we want to find out how long it will take for the new work crew of 4 people to complete the entire job. Let's denote the time in weeks as "x."

Total work done by the new crew of 4 people = 4 people * x weeks * 0.3043 work done per person in 1 week

Total work done by the new crew of 4 people = 1 job (as they will complete the entire job)

So, we have the equation:

4x * 0.3043 = 1

Now, solve for "x":

x ≈ 1 / (4 * 0.3043)

x ≈ 0.8225

Therefore, it would take a work crew of 4 people approximately 0.8225 weeks to do the same job. To convert this into days:

0.8225 weeks * 7 days/week ≈ 5.7575 days

So, it would take a work crew of 4 people approximately 5 days and 18 hours to complete the same job if each person in both crews works at the same rate as each other.

For more details of  work crew:

brainly.com/question/20323478

#SPJ2

Answer 2
Answer: 20  days per 3 people         for 4 people


20/3 * 4 = 26 & 2/3 days

Related Questions

Do political maps have legends and scales? and what is something interesting about them?
Each pair of polygons is similar. Determine the transformations taht map one figure onto the other. Then find the missing side measures.
Explain how an estimate helps you to place the decimal point when multiplying 3.7 x 5.1?
Yoyoyoyooyyoyoyoyyyoy I need help plz someone
Based on what you have learned about Malala’s viewpoints and setting, why is a blog a good way for Malala to speak up? Write two to four sentences explaining your answer.

Help me out please ...

Answers

Answer:

try 5

Step-by-step explanation:

Answer:5

Step-by-step explanation:

A lawn sprinkler spins in a circle. The sprinkler covers a radius of 4 feet. Which choice is the closest to the area of lawn that the sprinkler can cover?

Answers

Answer:

The correct answer is 50 feet

Step-by-step explanation:

Area= r^2*π = 4^2*π= 16π.

The final answer is 16π ft^2~

How do you find the nearest hundredth of a decimal number?

Answers

Round up if the previous digit is 5 or above, leave it the same (only the hundreth digit, erase all the other thousandths and such) if it is 4 or below

Is 7/8 or 11/10 closer to 1? How did you decide anybody help please?

Answers

Let

A-----> (7)/(8)

B-----> (11)/(10)

C-----> 1

we know that

Point A-------> Multiply numerator and denominator by 10

(7*10)/(8*10) =(70)/(80)

Point B-------> Multiply numerator and denominator by 8

(11*8)/(10*8) =(88)/(80)

Point C-------> Multiply numerator and denominator by 80

(1*80)/(1*80) =(80)/(80)

Find the distance Point A to Point C

(80)/(80) -(70)/(80) =(10)/(80)

Find the distance Point B to Point C

(88)/(80) -(80)/(80) =(8)/(80)

therefore

(8)/(80) < (10)/(80)

Point B is closer to Point C

(11)/(10) is closer to 1

the answer is

(11)/(10) is closer to 1

You can also figure it out by knowing that 7/8 is 1/8 away from 1 and 11/10 is 1/10 away from 1. since 1/10 is smaller than 1/8, you know that 11/10 is closer to 1 than 7/8.

0.45013 in scientific notation

Answers

When putting numbers into scientific notation, always put the decimal after the ones place. In this case, you would put the decimal after 4 and before 5 (in between). From there, you count how many decimal places you moved in order to change it into that form.

0.45013 would change to 4.5013 and you would have to multiply it by 10 to the negative power of 1 (you're only moving back one place).

4.5013 x 10^-1

Hope this helps :)

Which arrow is pointing to the horizontal axis title?a.
#1
b.
#2
c.
#3
d.
#4

Answers

Answer:

is there a graph which shows the axis title or the arrow pointing to the axis title if so i would love to help with this question !!!

Step-by-step explanation:

Angie <3 be the best you be different from the rest be inspired

Final answer:

The horizontal axis on a graph typically refers to the x-axis. The title of this axis is usually situated near the bottom of the graph. The provided question does not include a visual reference, making it impossible to accurately determine which arrow (#1, #2, #3, or #4) is pointing to the horizontal axis title.

Explanation:

Without a visual reference or context, it is not feasible to definitively identify which of the arrows (#1, #2, #3, or #4) is pointing to the horizontal axis title. In a Cartesian coordinate system used in mathematics, the horizontal axis typically refers to the x-axis, and the title of this axis typically provides information or labels what these x-values represent within the graph's context.

Rule of thumb says, if the options were positioned in such a way, the horizontal axis is typically positioned at the bottom of the graph. So it would most likely be either the arrow placed at the bottom or the one pointing towards the bottom of the image which would indicate the horizontal axis title.

Learn more about Horizontal Axis Title here:

brainly.com/question/31392544

#SPJ3