Answer: Green business
Explanation:
Green business is also referred to as the sustainable business, and it's a business which has a minimal negative impact on the environment.
Green industry businesses aim to use little energy, water, and other resources while cutting carbon emissions. The resources that are used are utilized in eco-friendly ways.
Since Jason works for a restaurant that serves only organic, local produce, the business can said to be a green business.
The home keys for the numeric keypad are 4 5 6
The fingers (Index, middle, and ring), on your right hand should always start on the 4 5 6 keys respectively. These keys are the home row keys for your numeric keypad. Each finger placed is responsible for a column of keys. For example, the middle finger is responsible for all the keys that lie in that column.
a. True
b. False
The statement that your networking contact list should be limited to family members is false. The term networking contact denotes professional contacts. Your networking list should include: connectors, experts in your filed, alumni or career services and people who support you.
Note that an intranet is a private network contained and used only by an organization.
True is your answer, for only the people who have access to it, are ablt to access the information.
hope this helps
If this is true or false, it would be true
Hope this helps
-AaronWiseIsBae
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.