We are required to calculate the number of days it would take the apprentice working alone
The number of days it takes the apprentice working alone is 6 days
let
Number of days taken for the carpenter to work alone = x
Number of days taken by the apprentice to work alone = 2x
Number of days taken to work together = 2 days
Work done per day Carpenter = 1/x
work done per day apprentice = 1/2x
work done per day together = 1/2
So,
work done per day together = Work done per day Carpenter + work done per day apprentice
1/2 = 1/x + 1/2x
1/2 = (2 + 1) / 2x
1/2 = 3/2x
cross product
1(2x) = 2(3)
2x = 6
x = 6/2
x = 3 days
Therefore,
Number of days taken by the apprentice to work alone = 2x
= 2(3)
= 6 days
Read more:
Answer:
6 days
Step-by-step explanation:
Let the time taken by Carpenter working alone = days
Then time taken by apprentice alone = Twice as that of taken by Carpenter = 2 days
Time taken working together = 2 days
Work done in one day working together =
Work done in one day by Carpenter working alone =
Work done in one day by apprentice working alone =
Work done in one day by Carpenter working alone + Work done in one day by Carpenter working alone = + = Work done in one day working together =
Time taken by Carpenter alone to complete the work = 3 days
Time taken by Apprentice alone to complete the work = 3 2= 6 days
Answer:
Step-by-step explanation:
Given that, r varies inversely with u. r=k÷u, k being the constant.
Therefore, k=8×5, ( after making k the subject of your formula).
This implies that k=40.
Now, according to the formula r=k÷u,
r=40÷55
Therefore, r=0.72
Answer:
-6 is not a natural number. It is an integer because of the negative symbol.
Hope this helped and have a great day!
(vote brainliest please)
Answer: no
explanation: because all natural numbers have to be positive
Two sevenths times eight thirds
Three eights plus one twelth
Answer:
Step-by-step explanation:
$26.25/3 scarves=$8.75/1 scarf
the cost of 1 scarf is $8.75
Answer:
I guess that you want to model the elevation of Lake Sam Rayburn.
During the summer, it is 165 ft above the sea level (the sea level is our position 0ft).
If it does not rain, the elevation of the lake decreases by 0.5ft each week.
So if we assume that there is no rain, we can write the elevation fo the lake as a linear relationship with slope equal to -0.5ft and y-intercept equal to 165ft.
L(w) = 165ft - 0.5ft*w
Where w is the number of weeks without rain, if we have 0 weeks without rain, then the level of the lake remains constant at 165ft above sea level,
L(0) = 165ft - 0.
1xl pieces can you get out if
you use all of them?
Answer:192
Step-by-step explanation:
Calculate the area l*w or s*s
Divide the two areas to get the number of 1*1 from 1 plywood then multiply by their number which is 6 here
4*8=32/1=32*6=192
You can get a total of 192 pieces of 1'x1' plywood from six 4'x8' pieces.
To find the total number of 1'x1' pieces that can be cut from the 4'x8' plywood pieces, we need to find the total area of plywood available and then divide it by the area of the desired pieces.
First, calculate the area of one piece of plywood: 4 feet x 8 feet = 32 square feet.
Since there are 6 pieces, the total area of plywood is 6 x 32 square feet = 192 square feet.
Since each 1'x1' piece has an area of 1 square foot, you can get 192 1'x1' piecesout of all the plywood.
#SPJ2