Answer:
Cycle Time = 10.19482 minute
Explanation:
From the question :
The Model E can be illustrated perfectly as shown below:
Process Time Required Predecessor Task Learning Rate
per Unit
A 9 82
B 12 A 86
C 18 B 81
D 9 C 90
E 12 D 80
F 17 E 88
G 14 F 83
H 12 G 85
I 8 H 82
Now For the minutes per week for each Process; we have :
Process Time Required Predecessor Learning Minutes
per Unit Task Rate (Week 16)
A 9 82 4.069096
B 12 A 86 6.564098
C 18 B 81 7.74841
D 9 C 90 5.9049
E 12 D 80 4.9152
F 17 E 88 10.19482
G 14 F 83 6.644165
H 12 G 85 6.264075
I 8 H 82 3.616974
The objective here is to determine the expected Cycle Time for Model E in Week 16
So, we can equally regard the Cycle Time = Bottleneck of Activity for Week 16.
Cycle Time = 10.19482 minute in as much as it is the the largest activity time for the week 16
Given that the demand per week is : = 247
The available time per week = 40 hours = 40 × 60 hours = 2400 minutes
Talk Time = Available Time Per Week/Demand Per Week
Talk Time = 2400/247
Talk Time = 9.716599
Thus; here the cycle time is greater than the talk time.
Answer:
If every work receives a tax rebate of $500 per person income tax the quantity of labor supplied will not increase because the rebate is a temporary
A 4.5% increase in marginal tax = 0.16 * 4.5 = 0.72 = 0.7 ( decrease in quantity of labor )
A 2% increase in marginal tax
= 0.16 * 2 = 0.32 = 0.3 ( decrease in quantity of labor )
A 15% increase
= 0.16 * 15 = 2.4 ( decrease in quantity of labor )
No increase = 0.16 = 0.16 ( quantity of labor supplied remains unchanged )
A reduction of 5%
= 0.16 * 5 = 0.8 ( increase in quantity of labor )
Explanation:
Tax elasticity of labor supply = 0.16
What percentage will the quantity of labor supplied increase in response to
A) $500 per person income tax rebate
percentage change in quantity supplied = (tax elasticity of supply) * (percentage change in tax rate ) If every work receives a tax rebate of $500 per person income tax the quantity of labor supplied will not increase because the rebate is a temporary measure and does not have an effect the tax rate in the long run.
B) A 4.5% increase in marginal tax
change in the quantity of labor = tax elasticity * increase marginal tax
0.16 * 4.5 = 0.72 = 0.7 ( decrease in quantity of labor )
A 2% increase in marginal tax
= 0.16 * 2 = 0.32 = 0.3 ( decrease in quantity of labor )
A 15% increase
= 0.16 * 15 = 2.4 ( decrease in quantity of labor )
No increase = 0.16 = 0.16 ( quantity of labor supplied remains unchanged )
A reduction of 5%
= 0.16 * 5 = 0.8 ( increase in quantity of labor )
Answer:
The answer is: 2500 employees
Explanation:
Giving the following information we need to calculate the number of employees:
Total production= 60000
Hours per worker= 160 hours
labor productivity= 0,15
It takes to a single employee= 1/0,15= 6,67 hours to make a heater.
Each worker produces=160/6,67=24 heaters a year.
Now we can calculate the number of workers:
60000/24= 2500 employees
Answer:
The correct answer is option (D)
Explanation:
Solution
Given that:
The present value of equity factor for 5 years at 12% discount are = 3.60478
Then,
The present value of servicing costing = -$500 * 3.60478 = -$1802.39
Thus,
The present value of cost to buy =- $18000
The total Present value = -18000 + 1802.39 = -$19802.39
So,
The equivalent annual annuity = total Present value / present value of equity factor
= -$19802.39 / 3.60478
= -$5493.37
Therefore, the equivalent annual annuity of this deal is -$5493.37
Options:
a.The rate of inflation will rise.
b.The rate of inflation will decline.
c.The rate of inflation will remain unchanged.
d.The rate of inflation may rise or decline
Answer:b.The rate of inflation will decline.
Explanation:Fixed exchange rate is a term used in Economics to describe the "pegging" or fixes the amount to which its own currency will trade with a popular currency like the United States Dollar. This will give investors,importers and exporters more stability and confidence as they will not be scared of indiscriminate fluctuations. WITH THIS CONFIDENCE THE RATE OF INFLATION WILL DECLINE AS INVESTORS WILL NOT BE UNDER PRESSURE TO HOARD GOODS OR REDUCE THE VOLUME OF PRODUCTS RELEASED TO THE MARKET AND CONSUMERS WILL NOT BE UNDER PRESSURE TO BUY.
Answer:
a. $3,000 Favorable
Explanation:
Variable cost variance is the difference between the budgeted variable cost and actual variable cost for a period.
Use following formula to claculate the variable cost variance
Variable cost variance = Budgeted Variable cost - Actual variable cost
Placing values in the formula
Variable cost variance = Budgeted Variable cost - Actual variable cost
Variable cost variance = $23,000 - $20,000
Variable cost variance = $3,000
As the actual cost is less than the budgeted cost, so the $3,000 is saved in respect of variable cost.
Answer:
4
Explanation:
The calculation of the process capability index is given below
Data provided in the question according to the question is as follows
USL = 27
LSL = 21
Now we take the average
X = (21 +27) ÷ 2
= 24
The standard deviation is 0.25
= min(USL - mean ÷ 3 × standard deviation , mean - LSL ÷ 3 × standard deviation)
After solving this the process capability index is 4