The earned value system starts with the time-phased costs that provide the project baseline, which is called the ___________.a. Planned budgeted value of work scheduled. b. Scheduled value of work completed. c. Planned budgeted value of work completed. d. Earned value of work scheduled. e. Scheduled value of work scheduled.

Answers

Answer 1
Answer:

Answer:

A. Planned budgeted value of work scheduled.

Explanation:

Earned Value system is a technique used in project management in estimating how well a project is doing in terms of the project budget and allocated schedule. It is used in estimating project efficiency in terms of the estimated deliverables. It helps in checking of the project is going according to "plan". Project efficiencies are measured against the baseline of a project which is the planned budgeted value of work with the aid of earned value system in order to quickly track any deviations in the project.


Related Questions

maxine epstein is married and claims one allowance. epstein earns $750 weekly and also receives bonus checks (separate from her regular wages). epstein earned a bonus of $3,500 and her employer withheld from the bonus at a 22% flat rate. compute epstein's total federal income tax withholding at the flat rate from the bonus.
Meg's company decided to build an additional factory in a small community. When the community started a protest because of the negative impact the factory would potentially have, Meg's company promised to prevent and pay for any negative impact to the community. It also offered to build a community park to balance out the negative impact the factory might cause. Which moral standard of social responsibility is the business observing?
The personal cultural orientation that questions whether the consumer avoids talking to strangers and prefers a routine is ________.
A Weak Dollarby The Columbus Dispatch, September 7, 1999If the price of buying a car starts rising in the United States, consumers may need to look no further than the dollar's recent slide against major foreign currencies.On the other hand, economically depressed Midwestern farmers may find it easier to sell surplus grain overseas if a weak dollar makes it cheaper for foreigners to buy U.S. goods.The dollar spent much of last week on the skids, flirting with its lowest level of the year against the Japanese yen...It also has lost ground to the euro.The passage MOST LIKELY relates toA)the national debt.B)the exchange rate.C)the inflation rate.D)the stock exchange
All of the following are considered equipment for a business EXCEPT:a. devices b. machines c. buildings d. tools

Which of the following groups on the Text Box Tools Format tab contains the command to create a drop cap?Text
Typography
Font
Alignment

Answers

Answer:

Text

Explanation:

In the Text box tools format tab, the text group contains the command to create a drop cap. A drop cap is large capital letter mostly used to decorate a document at the start of a section of the document. A drop cap is usually large as it can take up to 2 or more lines.

To insert a drop cap, choose the area to be changed in the section, opent the text box tools format tab and click drop cap.

Cheers.

Client satisfaction is related toa. making new friends
b. talking about problems
c. solving problems
d. making more money

Answers

It must be making more money by solving his problems :)

Which advantage do consumers gain from buying a vehicle rather than leasing it

Answers

They don't have to pay as much interest.

d.

"I would prefer to walk out of the deal in the end with something to show for the money I put in."

According to The Wedding Report, in 2010, the average wedding cost a little more than _____. twenty-four thousand dollars five thousand dollars eleven thousand dollars thirty thousand dollars

Answers

Answer:

The correct answer is twenty-four thousand dollars.

Explanation:

According to The Wedding Report, in 2010, the average cost of weddings was just over twenty-four thousand dollars. This is because the rental costs of the place where the wedding will take place are high, the decoration and lighting also raise the costs. The sound, music or band is also added to a list that varies according to the magnitude of the wedding. While there are some more ostentatious than others, the average is calculated by adding the total costs and dividing them into the number of weddings that took place in 2010.

Have a nice day!

The average wedding costs 24,000$ "According to The Wedding Report, in 2010 the average wedding cost a little more than $24,000." found this in my study guide :) I hope it helps.



The ease with which you can get your money out on an investment is known as its _____. liquidity risk rate or return opportunity cost

Answers

Liquidity is the ease with which you can get your money out of an investment.

Liquidity is defined as the ease of liquefying assets without causing significant impact on its price. Liquid assets are cash, cash equivalents, and other assets that can be easily converted into cash. Sellers and buyers of these assets are abundant.  

Buildings and other real estate properties are not liquid assets. This is because it is not easily converted into cash. Prices of these assets may vary depending on the availability of buyers that are interested in said properties. 


Your business needs a small database for storing simple names, addresses, and ID picture information for 1000 employees. The usage will be low, queries will occur every day, and the business wants the most suitable low cost solution available within AWS. Which database would you suggest

Answers

Answer:

Amazon Dynamo DB

Explanation:

Amazon DynamoDB can provide you with excellent and extremely fast access at a very small cost in your case. DynamoDB charges its fees based on usage, performance and storage, and your company requires low usage and a relatively small storage. DynamDB doesn't require a structured format nor it provides a dedicated infrastructure footprint.